Project details:

Segment: Industrial construction
Design office CSV Life Science
Completion:  October 2020

 

 

Project description:

The construction consists of two stages:

1. Construction of an office and laboratory building
Building D
Implementation period: 12/04/2018 – 31/03/2020.
Total area: 9,314 m2
Volume: 34 800 m3

The building consists of a laboratory, office part and technical rooms.
The building has 3 floors, 1 underground floor.

2. Construction of a new production and logistics center
Buildings A, B, C
Completion date: 15.08.2018 – 31.10.2020.
Total area: 25 996 m2
Volume: 146 910 m3

Building A – warehouse
1 above-ground floor

Building B consists of a laboratory and office part as well as a technical zone and a boiler room.
4 floors, 1 underground floor

Building C consists of a laboratory, office part and technical zone
3 floors, 1 underground floor